Tenders Report of the Country Projects

 

Country-Plan Tenders

محطة طاقة جديدة هيدروليكية بأسيوط قدرة 40 ميجاوات

Works initiated by the Ministry of Electricity & Energy to build a 40 MW hydraulic power station at Assuit barrage location.

Saturday, December 27, 2003
Al Alam Al Yom
Assiut
Works are said to have been initiated by the Ministry of Electricity & Energy to build a 40 MW hydraulic power station at Assuit barrage location. Project is backed by Euro 51 million soft loan. Implementing agency is the Hydraulic Power Projects Authority, chaired by Eng. Mohamed Abdel Monem. Upon completion, the project would annually save L.E. 25 million worth of traditional fuel.

Beneficiary Sectors
- Electromechanical Works
      Electromechanical Works
- Energy
      Generation